Glossary of Construction Scheduling Terms
- Home
- Glossary of Construction Scheduling Terms
Activity
Activity Code
An alphanumeric identifier used to group and filter activities. Each activity is assigned a code for categorization and reporting.
Activity Relationship
A logical connection between two activities, defining their sequence. The four relationship types are:
FS (Finish-to-Start) – Successor cannot start until predecessor finishes.
SS (Start-to-Start) – Successor cannot start until predecessor starts.
FF (Finish-to-Finish) – Successor cannot finish until predecessor finishes.
SF (Start-to-Finish) – Successor cannot finish until predecessor starts.
Baseline Schedule
Constraint
Contract Completion Date
The date defined in the contract by which all project work must be completed.
Critical Activity
An activity on the critical path with zero float; any delay will directly impact project completion.
Critical Path
The longest sequence of dependent activities through the schedule with the least float, determining the earliest possible project completion date. It may shift during execution due to progress or changes.
Current Schedule
Data Date (As-of Date)
Duration
Finish-to-Start (FS)
A common logic relationship where a successor begins only after the predecessor finishes.
Finish-to-Finish (FF)
Float
A successor cannot finish until the predecessor finishes.